A test manager informs a project manager about a one-week schedule delay to complete the testing phase. What should the project manager do next? Question
A test manager informs a project manager about a one-week schedule delay to complete the testing phase. What should the project manager do next? Question 13 options: 1) Fast-track the schedule 2) check whether the task is on the critical path 3) negotiate with the customer for a change in the schedule 4) crash the schedule