A . ) Using the data below, calculate the Crash Cost per week for each Activity. B . ) If you had to crash the

A.) Using the data below, calculate the Crash Cost per week for each Activity.
B.) If you had to crash the project by 5 days at the minimum cost, which Activites would you crash? What would the total crash cost be?
Time (Wks) Cost ($)
Activity Normal Crash Normal Crash Critial Path
A 4240007000 NO
B 5320004000 YES
C 2110001500 YES
D 6450009000 NO
E 3230005000 YES
F 4215003000 YES

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: Joseph Heagney

4th Edition

0814417485, 978-0814417485

More Books

Students also viewed these General Management questions

Question

=+22. Energy investment decisions.

Answered: 1 week ago

Question

=+1. What is the brand's character or personality?

Answered: 1 week ago

Question

=+3. Who is the audience?

Answered: 1 week ago

Question

=+4. What do they (audience members) currently think?

Answered: 1 week ago