Question

1 Approved Answer

A week prior to the project kick-off call, a Project Manager meets with a key project resource to understand how complex the project deliverables are.

  • A week prior to the project kick-off call, a Project Manager meets with a key project resource to understand how complex the project deliverables are. The resource expresses concern and worries regarding the deliverables. Which of the following the Project Manager do to ensure that the deliverables are realistic?
  • a. Perform a feasibility study, and then assess the results
  • b. Identify threats and preventive actions by conducting a risk assessment
  • c. Note the concerns in the issue log to review at a later date
  • d. Discuss the resource's concerns with the sponsor, and modify the project charter


 

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render, Paul Griffin

1st Canadian Edition

132687585, 978-0133357516, 133357511, 978-0132687584

More Books

Students also viewed these General Management questions

Question

Assess control risk for a revenue process. L-987

Answered: 1 week ago

Question

What is JIT?

Answered: 1 week ago