A work cell is scheduled to build 250 digital light processor (DLP) assemblies each week. These assemblies
Fantastic news! We've Found the answer you've been seeking!
Question:
A work cell is scheduled to build 250 digital light processor (DLP) assemblies each week. These assemblies are later installed into home theatre projection systems. The work cell has 16 hours of productive work eads day, seven days per week. What is takt time for this cell?