A worker works for 40 hours on a business renovation project . The rates of overhead was 200 percent of of direct labour, and the
A worker works for 40 hours on a business renovation project . The rates of overhead was 200 percent of of direct labour, and the direct labour rate was $ 40 per hour . What is the total cost of the job? Select one: a. $ 3200 b. $ 2000 c. $ 4800 d. $ 1600