A written construction contract, under which a contractor agreed to build a new house for a landowner at a fixed price of $ 2 0
A written construction contract, under which a contractor agreed to build a new house for a landowner at a fixed price of $ contained the following provision:
Prior to construction or during the course thereof, this contract may be modified by mutual agreement of the parties as to extras or other departures from the plans and specifications provided by the landowner and attached hereto. Such modifications, however, may be authorized only in writing, signed by both parties.
During construction, the contractor incorporated into the structure overhanging gargoyles and other extras orally requested by the landowner for orally agreed prices in addition to the contract price. The landowner subsequently refused to pay anything for such extras, amounting to $ at the agreed prices, solely on the ground that no written, signed authorization for them was ever effected.
If the contractor sues the landowner on account of the extras who will prevail?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started