Question

1 Approved Answer

A written construction contract, under which a contractor agreed to build a new house for a landowner at a fixed price of $ 2 0

A written construction contract, under which a contractor agreed to build a new house for a landowner at a fixed price of $200,000, contained the following provision:
Prior to construction or during the course thereof, this contract may be modified by mutual agreement of the parties as to extras or other departures from the plans and specifications provided by the landowner and attached hereto. Such modifications, however, may be authorized only in writing, signed by both parties.
During construction, the contractor incorporated into the structure overhanging gargoyles and other extras, orally requested by the landowner for orally agreed prices in addition to the contract price. The landowner subsequently refused to pay anything for such extras, amounting to $30,000 at the agreed prices, solely on the ground that no written, signed authorization for them was ever effected.
If the contractor sues the landowner on account of the extras, who will prevail?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of Management

Authors: Andrew J. DuBrin

9th Edition

538478233, 2900538478235, 978-0538478236

More Books

Students also viewed these General Management questions