a) You have a project sprints into 1-week long sprints. The project start date is 1 May 2022. b) In your project 3 resources, A,
a) You have a project sprints into 1-week long sprints. The project start date is 1 May 2022.
b) In your project 3 resources, A, B, C each working 5 days.
Each working 5 days/40 hours a week in sprint. What will be the total work for sprint 1
c) Baseline set to 1 May 2022.
d) each resources complete 20% of his task daily.
e) on day 3(3 May 2022), A completes 5% of his task- comulative actual work is left behind.
f) What will be task burn down and work down for sprint 1