A=10, B=7, C=8, D=4, E=5. When is the earliest time that Activities A-D can start? What about Activity E? If you were a project manager
A=10, B=7, C=8, D=4, E=5. When is the earliest time that Activities A-D can start? What about Activity E? If you were a project manager managing this schedule excerpt, what concerns might you have, if any, regarding the risk of Activity E beginning on time? What general rule or management principle could you derive from this network excerpt?