Question
1 Approved Answer
Aarons chairs is in the process of preparing a production cost budget for august actual cost in july for 120 chairs : material cost 4770
Aarons chairs is in the process of preparing a production cost budget for august
actual cost in july for 120 chairs :
material cost 4770
labor cost 2630
rent 1500
depreciation 2500
other fixed cost 3600
materials and labor are the only variable cost . If production sales are budgeted to change to 130 in august , how much is the expected total variable cost on the august budget ?