Question
AB Corp. entered into a contract with XY Corp. whereby the former agreed to construct the research and laboratory facilities of the latter. Under the
AB Corp. entered into a contract with XY Corp. whereby the former agreed to construct the research and laboratory facilities of the latter. Under the terms of the contract, AB Corp. agreed to complete the facility in 18 months, at the total contract price of P10 million. XY Corp. paid 50% of the total contract price, the balance to be paid upon completion of the work. The work started immediately, but AB Corp. later experienced work slippage because of labor unrest in his company. AB Corp.'s employees claimed that they are not being paid on time; hence, the work slowdown. As of the 17th month, work was only 45% completed. AB Corp. asked for extension of time, claiming that its labor problems is a case of fortuitous event, but this was denied by XY Corp. When it became certain that the construction could not be finished on time, XY Corp. sent written notice canceling the contract, and requiring AB Corp. to immediately vacate the premises. a) Can the labor unrest be considered a fortuitous event? b) Can XY Corp. unilaterally and immediately cancel the contract? c) Must AB Corp. return the 50% down-payment?*
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started