ABC Co. makes tables which are sold in kits to be assembled by the customer. The Master Production Schedule calls for the manufacture of 80

ABC Co. makes tables which are sold in kits to be assembled by the customer. The Master Production Schedule calls for the manufacture of 80 and 200 tables in Weeks 5 and 6 respectively:

Week 1 2 3 4 5 6
MPS Quantity -- -- -- -- 80 200

The components of the table (tops and legs) have the following data:

Operation

Top (1 needed)
Machine Setup Time (min) Run Time (min)
1 Saw 10 5
2 Planer 40 20

Operation

Leg (4 needed)
Machine Setup Time (min) Run Time (min)
1 Saw 10 1
2 Sander 52.5 17

The lot size for both tops and legs is 100 units. Lead time for every operation is 1 week. Historically the load proportions on the machines have been as follows:

Machine Historical Load Distribution
Saw 15%
Planer 25%
Sander 60%

Standard time to make a table is 100 minutes.

  1. Using Overall Factors (CPOF) method determine capacity requirements in Week 4 and 5 for individual resources. (3 points)

Capacity Requirement in Week 5:

Saw:

Planer:

Sander:

Total:

Capacity Requirement in Week 6:

Saw:

Planer:

Sander:

Total:

  1. Using Capacity Bills method determine capacity requirements in Week 4 and 5 for individual resources. (5 points)

HINT: Compute Standard Times using the following templates:

Operation

Top Time/Top Time/Table
Machine Setup Time (min) Run Time (min)
1 Saw 10 5
2 Planer 40 20

Operation

Leg Time/Leg Time/Table
Machine Setup Time (min) Run Time (min)
1 Saw 10 1
2 Sander 52.5 17

Machine Time/Table
Saw
Planer
Sander
Total

Capacity Requirement in Week 5:

Saw:

Planer:

Sander:

Total:

Capacity Requirement in Week 6:

Saw:

Planer:

Sander:

Total:

  1. Using Resource Profiles method determine capacity requirements in Week 4 and 5 for individual resources. (8 points)

Capacity Requirement in Week 5:

Saw:

Planer:

Sander:

Total:

Capacity Requirement in Week 6:

Saw:

Planer:

Sander:

Total:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

4th Edition

0749475811, 978-0749475819

More Books

Students also viewed these General Management questions

Question

What is visionary leadership?

Answered: 1 week ago

Question

define what is meant by the term human resource management

Answered: 1 week ago