ABC Company is evaluating a project that has a beta coefficient equal to 1.5. The risk-free rate is 3 percent and the market risk premium
ABC Company is evaluating a project that has a beta coefficient equal to 1.5. The risk-free rate is 3 percent and the market risk premium is 7 percent. The project will require an investment of $400,000, and will generate $155,000 in after-tax operating cash flows for the next three years. Should ABC Company embark on the project? Why