ABC Company's standard and actual costs per unit for the most recent period, during which 200 units were actually produced, are given below: Standard Actual
ABC Company's standard and actual costs per unit for the most recent period, during which 200 units were actually produced, are given below:
| Standard | Actual |
Materials: |
|
|
Standard: 2 metres at $1.50 per metre | $3.00 |
|
Actual: 2.1 metres at $1.60 per metre |
| $3.36 |
Direct labour: |
|
|
Standard: 1.5 hrs. at $6.00 per hr. | 9.00 |
|
Actual: 1.4 hrs. at $6.50 per hr. |
| 9.10 |
Variable overhead: |
|
|
Standard: 1.5 hrs. at $3.40 per hr. | 5.10 |
|
Actual: 1.4 hrs. at $3.10 per hr. | _____ | 4.34 |
Total unit cost | $17.19 | $16.80 |
There were no inventory of materials at the beginning or end of the period. Required: From the above information, compute the following variances. Show whether the variance is favourable (F) or unfavourable (U): (10 marks)
a) What is the materials price variance?
b) What is the materials quantity variance?
c) What is a possible explanation for the direct material variance?
d) What is the direct labour rate variance?
e) What is the direct labour efficiency variance?
f) What is a possible explanation for the direct labour variance?
g) What is the variable overhead spending variance?
h) What is the variable overhead efficiency variance?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started