ABC Construction has the following contract: Contract price 1,000,000 Cost incurred cost to complete Dec 31 2017 200,000 600,000 Dec 31 2018 350,000 250,000 Dec
ABC Construction has the following contract: Contract price 1,000,000 Cost incurred cost to complete Dec 31 2017 200,000 600,000 Dec 31 2018 350,000 250,000 Dec 31 2019 300,000 850,000 Billings Cash Received Dec 31 2017 250,000 200,000 Dec 31 2018 400,000 350,000 Dec 31 2019 350,000 450,000 1,000,000 1,000,000 A. Prepare a % of completion schedule for the three years B. Prepare journal entries for 3 years