ABC Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one
ABC Fast Food has four activities in serving a customer: greet customer, take order, process order, and deliver order. Each activity is staffed by one employee (for a total of four employees). The processing time for each activity is given as follows: Activity Processing time per customer Greet customer 2 seconds Take order 30 seconds Process order 60 seconds Deliver order 5 seconds What is the capacity of this process