Question
ABC Inc manufactures office chairs. Presently the company assigns overhead to each product using direct labor hours to calculate a plantwide rate. The following information
- ABC Inc manufactures office chairs. Presently the company assigns overhead to each product using direct labor hours to calculate a plantwide rate.
The following information is available for the upcoming years:
Estimated factory overhead | $890,000 |
Estimated direct labor hours | 10,000 |
The company is considering implementing an activity-based costing system and has identified three activities. Resource drivers are used to assign costs to each activity.
The following information about each activity is available
Activity | Estimated Costs | Cost Drivers | Total Estimated Driver |
Material handling | $300,000 | Parts | 60,000 |
Assembly | $400,000 | Machine hours | 50,000 |
Finishing | $190,000 | Direct labor hours | 10,000 |
One of the models that the company produces uses the following resources:
| OC- 16 |
Parts | 24 |
Machine Hours | 4 |
Direct labor hours | 3 |
Using the above information, answer the following questions.
- The plantwide predetermined overhead rate using direct labor hours as the cost driver is $________ per direct labor hour.
- Assume that the actual direct labor hours were 12,000 direct labor hours. If the company uses the plantwide rate, then the total applied overhead would be $_________.
- Using the plantwide overhead rate, the total overhead applied to one unit of OC-16 is $_________.
- If the company decided to use activity-based costing, then the overhead rate for Material Handling would be $_______ per part.
- If the company decided to use activity-based costing, then the overhead rate for Assembly would be $_______per machine hour.
- If the company decided to use activity-based costing, then the overhead rate for Finishing would be $_______per direct labor hour.
- Using the activity-based costing system, the total overhead applied for all activities go one unit of OC-16 is $________.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started