Question

1 Approved Answer

ACC-650 FINAL EXAM Question 9 Oriole Creations purchased 8300 feet of copper tubing at a price of $2.80 per foot and used 8000 feet during

ACC-650 FINAL EXAM Question 9 Oriole Creations purchased 8300 feet of copper tubing at a price of $2.80 per foot and used 8000 feet during the period. The standard quantity allowed for the units produced is 7800 and the standard price of the copper tubing is $3.00 per foot. What is Oriole Creations' direct materials quantity variance for the period?

Select answer from the options below $560 unfavorable

$600 unfavorable

$900 unfavorable

$1500 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Sound Investing, Chapter - Classification Deceit

Authors: Kate Mooney

2nd Edition

0071719385, 9780071719384

More Books

Students also viewed these Accounting questions

Question

What is ethnocentric bias?

Answered: 1 week ago