According to the project's current status report, can you write six items for Management attention explaining reasons? What needs to be done? What do we
According to the project's current status report, can you write six items for Management attention explaining reasons? What needs to be done? What do we want from management?
Status Item | Previous Status | Current Status | Details & Rationale |
Overall Project Status | Red | Yellow | Considering that time is the main constraint of the project, the previous status was considered red because there was a significant delay in the execution of the project due to technological difficulties faced by the team. Using appropriate measures, the status was changed to yellow. The scope and quality of the project is on track. |
Quality / Scope Status | Green | Green | The Quality and Scope of the project is progressing well. |
Schedule Status | Red | Yellow | The previous status was considered red because there was a significant delay in the execution of the project due to technological difficulties faced by the team. After consulting the senior management, this decision was taken to fast-track the project by allotting appropriate resources which would help reduce the delay to the project. Some tasks however would be delivered late hence the current schedule status is Yellow. |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started