The Smith family wishes to build a new home on a budget of $350,000, and has received estimates for each of the construction components from
The Smith family wishes to build a new home on a budget of $350,000, and has received estimates for each of the construction components from the General Contractor, as given in the table on the following page. Create a simulated model of the construction costs, and use it to answer the questions below. Submit both a word document with the answers and a supporting Excel file OR a word document with the answers and screenshots of your simulation output graphs from @Risk.
You can access @Risk on the Krannert Virtual Server at virtual.krannert.purdue.edu. For any issues connecting, please contact the Krannert Computing Center directly.
1) Based on the most likely cost estimates, what is the expected cost of the building the house with only the mandatory items, and how does it compare to the budget?
2) Simulate the cost of building the house in @Risk or similar software. What is the expected cost of building the house using this method? Which should the Smith family use to make a decision? Do not just describe the difference in methods, explain why the results are different.
3) What is the probability that the Smiths will exceed their budget of 350K with only the mandatory items?
4) If the Smiths include all three of the optional items, how much would they need to budget to be 90% certain they could meet all costs?
Mandatory Items
Architect $27,000 $40,000 $51,000
Bath Fixtures $7,000 $8,000 $12,000
Built-in Appliances $1,600 $2,000 $3,500
Cabinets $5,000 $6,000 $10,000
Carpeting $4,000 $5,000 $7,000
Doors $3,500 $4,000 $8,000
Excavation $2,500 $2,500 $5,000
Finish Carpentry $7,000 $7,500 $10,000
Finish Hardware $1,250 $1,500 $2,000
Foundation $22,000 $25,000 $30,000
Garage Doors $2,700 $3,000 $4,500
Gas Fireplaces $1,700 $2,000 $3,000
General Contractor $30,000 $40,000 $55,000
Heating and Cooling $10,000 $12,000 $15,000
Insulation $3,750 $4,000 $5,500
Painting $2,750 $3,000 $4,500
Plumbing $6,200 $7,000 $8,500
Roofing $11,500 $12,000 $15,000
Rough Carpentry $110,000 $120,000 $150,000
Windows $18,500 $20,000 $27,000
Wiring $6,000 $6,500 $8,500
Optional Items
Countertops $4,000 $6,000 $9,000
Flooring $9,000 $10,000 $13,000
Lighting Fixtures $2,750 $3,000 $6,000
Step by Step Solution
3.37 Rating (147 Votes )
There are 3 Steps involved in it
Step: 1
After stimulating the cost of building the house in RISK the cost of the building is 35092157 Failur...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started