Ackerman's Garage uses standards to plan and control labor time and expense. The standard time for an engine tune-up is 3.5 hours, and the standard
Ackerman's Garage uses standards to plan and control labor time and expense. The standard time for an engine tune-up is 3.5 hours, and the standard labor rate is $15 per hour. Last week, 24 tune-ups were completed. The labor efficiency variance was 6 hours unfavorable, and the labor rate variance totaled $81 favorable.
Required:
a. Calculate the actual direct labor hourly rate paid for tune-up work last week.
b. Calculate the dollar amount of the labor efficiency variance.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started