Acme Companys production budget for August is 19,500 units and includes the following component unit costs: direct materials, $8.00; direct labor, $12.00; variable overhead, $6.00.
Acme Companys production budget for August is 19,500 units and includes the following component unit costs: direct materials, $8.00; direct labor, $12.00; variable overhead, $6.00. Budgeted fixed overhead is $52,000. Actual production in August was 21,450 units.
Required:
Prepare a flexible budget that would be used to compare against actual production costs for August. (Round "Cost per unit" to 2 decimal places.)