Acme Metal produces gear shafts. Currently, the gear shafts are produced in batches of twenty. Materials necessary to produce one batch of twenty are brought

Acme Metal produces gear shafts. Currently, the gear shafts are produced in batches of twenty. Materials necessary to produce one batch of twenty are brought to the cutting department, where they sit for an average of 10 minutes before cutting takes place. It takes eight minutes to cut the materials for each unit. Once the entire batch is cut, it is moved to the welding department. After a ten-minute wait, a computerized welding machine is setup to weld the parts in the batch. The 10-minute wait time includes travel time from cutting and is in addition to the time required to setup the welder. After the entire batch of 20 is welded, it is moved to the grinding department. Due to the backlog in grinding, it takes an average of 10 hours (plus the 10 minute travel time between departments) before work begins on the batch in the grinding department. After grinding is completed, the batch moves to buffing and packing. When the entire batch is completed the parts are shipped to the customer or moved to the finished goods warehouse. At any one time there is usually one batch being worked on in each department, one batch waiting at the welding department and two batches waiting at the grinding department.

20 per Batch 10 minute wait CUT 8 minutes each BUFF & PACK 10 minutes each 10 minute walt 10 minute wait GRIND 15 minutes eac

A) What is the lead-time (throughput time) for Acme Metal to produce a batch of 20 gear shafts?

B) How many gear shafts can Acme Metal produce per hour?

C) How many gear shafts on average are in work in process?

D) The direct material cost averages $75 for each gear shaft. Assume that direct labor time equals the process time for each process (e.g., the direct labor time for welding is 6 minutes per unit). If Acme Metal has a standard direct labor rate of $20 per hour, and they assign overhead at a standard rate of $180 per direct labor hour, what is the standard cost for each gear shaft?
 

20 per Batch 10 minute wait CUT 8 minutes each BUFF & PACK 10 minutes each 10 minute wait 10 minute wait WELD GRIND 15 minutes each 6 minutes each, 20 minute setup for batch 610 minute wait

Step by Step Solution

3.56 Rating (167 Votes )

There are 3 Steps involved in it

Step: 1

A Lead time is the amount of time that passes from the start of a process until its conclusion Companies review lead time in manufacturing supply chain management and project management during preproc... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Microeconomics

Authors: Robert Pindyck, Daniel Rubinfeld

8th edition

978-0132870436, 132870436, 013285712X, 978-0133371178, 133371174, 978-0132857123

More Books

Students also viewed these Accounting questions