Acquisition of Land and Building On February 1, 2016, Edwards Corporation purchased a parcel of land as a factory site for $100,000. It demolished an
Acquisition of Land and Building
On February 1, 2016, Edwards Corporation purchased a parcel of land as a factory site for $100,000. It demolished an old building on the property and began construction on a new building that was completed on October 2, 2016. Costs incurred during this period are:
Demolition of old building | $ 8,000 |
Architects fees | 25,000 |
Legal fees for title investigation and purchase contract | 4,000 |
Construction costs | 650,000 |
Edwards sold salvaged materials resulting from the demolition for $2,000.
Required:
1. At what amount should Edwards record the cost of the land and the new building, respectively?
If an input box should be blank, enter a zero.
Land | Building | |
Purchase price of land | $ | $ |
Demolition of old building | ||
Architect's fees | ||
Legal fees | ||
Construction costs | ||
Salvaged materials | ||
Total | $ | $ |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started