ACS Company made the following expenditures in connection with the construction of its new cross fit facility: Architects fees 9,000 Cash paid for land and
ACS Company made the following expenditures in connection with the construction of its new cross fit facility:
Architects fees | 9,000 |
Cash paid for land and old building | 140,000 |
Removal of old building | 20,000 |
Survey to site the new building | (8,000) |
Legal fees for title search | 1,000 |
Excavation for construction of basement | 2,500 |
Machinery purchased | 72,000 |
Storage charges on machinery because building was not ready when machinery was delivered | 600 |
Freight on machinery purchased | 2,000 |
Hauling charges to deliver machinery from storage to new building | 800 |
Construction costs of new building | 615,000 |
Landscaping | 7,050 |
Installation of machinery | 9,000 |
Prepare a schedule showing the amounts to be recorded as Land, Building, and Machinery and Equipment and Expenses.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started