Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Activi Normal Normal Minimum Cost to Immediate ty Time Cost ($) Time expedite Predecessor (days) (days) per day ($) S ABCDEFGI 4 1000 3
Activi Normal Normal Minimum Cost to Immediate ty Time Cost ($) Time expedite Predecessor (days) (days) per day ($) S ABCDEFGI 4 1000 3 300 None 7 1400 4 200 None 5 2000 4 700 None 6 1200 5 200 A 3 900 2 200 B 11 2500 6 250 C 4 800 3 650 D, E H 3 300 1 100 F, G Under normal conditions, what is the critical path? Under normal conditions, what is total project cost When the project will be finished? If the project must be finished in 14 days, what would you recommend?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started