1 Approved Answer
Activities G , P , and R are the immediate predecessors for activity W . If the earliest finish times for the three are 1
Activities G P and R are the immediate predecessors for activity W If the earliest finish times for the three are and then the earliest start time for W
a is
b is
c is
d Cannot be determined.