Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 13, 14, and 12,
Activities G, P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 13, 14, and 12, then what is the earliest start time for W? O 12 O 13 O 14 O cannot be determined