Activities on non-critical paths in a network diagram..... are not critical because the project team has prior experience with that kind of activities. always have
Activities on non-critical paths in a network diagram..... are not critical because the project team has prior experience with that kind of activities. always have free float of more than zero time units. generally contain total float of more than zero time units. are not critical because they will never generate any deliverable of the project that is technically critical to the success of the project