activities remaining before the new product can be brought to the market. The project network is as follows: The activity time estimates ( in weeks

image text in transcribed
activities remaining before the new product can be brought to the market. The project network is as follows:
The activity time estimates ( in weeks ) ?are as follows:
Activity
Optimistic
A
B
C
D
E
F
G
H
I
J
Most Probable
4 . 0
3 . 5
5 . 0
3 . 0
1 0 . 0
8 . 5
6 . 0
6 . 0
2 . 5
5 . 0
Pessimistic
5 . 0
7 . 0
6 . 0
4 . 0
1 4 . 0
1 2 . 5
7 . 5
1 3 . 0
6 . 0
6 . 0 a . ?Develop an activity schedule for this project and identify the critical path activities.
If required, round your answers to two decimal places. Enter " 0 " ?if your answer is zero.
Activity
Expected Time
Variance. What is the probability that the project will be completed so that Landon Corporation may introduce the new product within 2 5 ?weeks? Within 3 0 ?weeks?
Expected project completion time =
weeks. If required, round your answer to two decimal places.
? 2 =
. ?If required, round your answer to two decimal places.
?weeks
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Munson Young And Okiishi's Fundamentals Of Fluid Mechanics

Authors: Philip M. Gerhart, Andrew L. Gerhart, John I. Hochstein

8th Edition

1119080703, 978-1119080701

More Books

Students also viewed these General Management questions