Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks. The crash time for Activity A
Activity A has a standard cost of $500 and the standard time to complete Activity A is 5 weeks. The crash time for Activity A is 3 weeks and the crash cost is $600. What is the crash cost per week for Activity A?