Activity A is the first activity and has a duration of 4 days. Activity A has two successors B and C. B has a duration
Activity A is the first activity and has a duration of 4 days. Activity A has two successors B and C. B has a duration of 3 days and C has a duration of 4 days. B and C are both predecessors of Activity E. E has a duration of 5 days. D has one predecessor - activity B and has a duration of 7 Days. What is the critical time? 14 days 12 days 17 days 18 days