Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack time for A1? (HInt: All activities on

Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the slack time for A1? (HInt: All activities on the critical path are critical activities and such activities have zero slack