Question
1 Approved Answer
Activity Activity Pool Cost Activity Base Procurement $ 1 2 , 6 0 0 Number of purchase orders Scheduling 9 0 , 0 0 0
Activity Activity Pool Cost Activity Base
Procurement $ Number of purchase orders
Scheduling Number of production orders
Materials handling Number of moves
Product development Number of engineering changes
Total cost $
The estimated activitybase usage and unit information for two product lines was determined as follows:
Number of
Purchase Orders Number of
Production Orders Number of
Moves Number of
Engineering Change Orders
Units
Ovens
Refrigerators
Totals
a Determine the activity rate for each activity cost pool.
Procurement per purchase order $fill in the blank
Scheduling per production order $fill in the blank
Materials handling per move $fill in the blank
Product development per engineering change order $fill in the blank
b Determine the activitybased cost per unit of each product. Round the per unit rates to the nearest cent.
Ovens $fill in the blank per unit
Refrigerators $fill in the blank per unit
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started