Activity Availability, Capacity Used, Unused Capacity Corazon Manufacturing Company has a purchasing department staffed by five purchasing agents. Each agent is paid $ 3 0
Activity Availability, Capacity Used, Unused Capacity
Corazon Manufacturing Company has a purchasing department staffed by five purchasing agents. Each agent is paid $ per year and is able to process purchase orders. Last year, purchase orders were processed by the five agents.
Required:
Calculate the activity rate per purchase order.
$ per purchase order
Calculate, in terms of purchase orders, the:
a Total activity availability purchase orders
b Unused capacity purchase orders
Calculate the dollar cost of:
a Total activity availability $
b Unused capacity $
Express total activity availability in terms of activity capacity used and unused capacity. Express total activity availability in terms of activity capacity used and unused capacity.
Purchase orders
Total activity availability
Activity capacity used
Unused capacity
Dollars cost
Total activity availability
Activity capacity used
Unused capacity
$ $ $
What if one of the purchasing agents agreed to work half time for $
a How many purchase orders could be processed by four and a half purchasing agents?
purchase orders
b What would unused capacity be in purchase orders?
purchase orders
Feedback
Check My Work
& Activity availability Activity output Unused capacity
Cost of activity supplied Cost of activity used Cost of unused activity
Cost of activity supplied Cost of activity used Cost of unused activity
Activity availability Activity output Unused capacity
Cost of activity supplied Cost of activity used Cost of unused activity
Activity availability Activity output Unused capacity
See Cornerstone
Corazon Manufacturing Company has a purchasing department staffed by five purchasing agents. Each agent is paid $ per year and is able to process purchase orders. Last year, purchase orders were processed by the five agents.
Required:
Calculate the activity rate per purchase order.
$ per purchase order
Calculate, in terms of purchase orders, the:
a Total activity availability purchase orders
b Unused capacity purchase orders
Calculate the dollar cost of:
a Total activity availability $
b Unused capacity $
Express total activity availability in terms of activity capacity used and unused capacity. Express total activity availability in terms of activity capacity used and unused capacity.
Purchase orders
Total activity availability
Activity capacity used
Unused capacity
Dollars cost
Total activity availability
Activity capacity used
Unused capacity
What if one of the purchasing agents agreed to work
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started