Question
Activity Based Costing Project Autotech Manufacturing Product Costs The staff accountant for Sergeant Consulting Group has uncovered the following costs and activities associated with the
Activity Based Costing Project
Autotech Manufacturing Product Costs
The staff accountant for Sergeant Consulting Group has uncovered the following costs and activities associated with the two products.
Table 1:
Part 127
Part 234
Production
500,000
100,000
Selling Price
$31.86
$24.00
Prime costs per unit
$9.53
$8.26
Number of production runs
100
200
Receiving orders
400
1,000
Machine hours
125,000
60,000
Direct labor hours
250,000
22,500
Engineering hours
5,000
5,000
Material moves
500
400
Overhead is allocated using a plant-wide rage based on direct labor hours.
Preliminary analysis of costs by Sergeant Consulting Group revealed that similar costs can be categorized into the following cost pools. Setup costs are costs that occur each time a new production run is made. They involve retooling and reconfiguring the machines and technology. Material handling costs include the equipment and personnel required to transport materials from supplier trucks to the machines. Typically, materials are taken to a storage area before being transported to machines. Each production run will need new materials and materials may also be transported during production runs. Machine costs primarily include depreciation and machine maintenance. Although the machines are depreciated using accelerated depreciation schedules, typically the machine wears out from use and are replaced before they become obsolete.
Receiving costs include the costs of clerical and technical help associated with the processing of each order received from a customer. Engineering costs include the technical support staff that implement design changes in the part, manage processes to maintain quality, and provide technical information on the product. The engineering staffs maintain a record of the amount of time spent on each product. General plant costs include all the other administrative costs not included in the other cost pools.
Table 2:
Overhead Cost Pools
Setup costs
$240,000
Material handling costs
900,000
Machine costs
1,750,000
Receiving costs
2,100,000
Engineering costs
1,500,000
General plant costs
500,000
Total
$6,990,000
ABC Project-Analysis
Part 1: Compute overhead and gross margin using traditional costing
Per Unit
Part 127
Part 234
Overhead/unit
$
$
Gross Margin: Selling Price/unit
$
$
Direct costs/unit
$
$
Overhead/unit
$
$
Gross margin/unit
$
$
Total
Part 127
Part 234
Total Profit
$
$
Part 2: Select the best-cost driver from Table 1 and compute overhead rates for each cost pool.
Cost pool
Cost Driver
Overhead rate
Setup costs
$
Material handling costs
$
Machine costs
$
Receiving costs
$
Engineering costs
$
General plant costs
$
Part 3: Compute overhead cost and gross margin using Activity-based Costing
Per Unit
Part 127
Part 234
Overhead/unit
$
$
Gross Margin: Selling Price/unit
$
$
Direct costs/unit
$
$
Overhead/unit
$
$
Gross margin/unit
$
$
Total
Part 127
Part 234
Total Profit
$
$
Part 4: Recommendations- Increase in price for Product 234 by 25%
Per Unit
Part 127
Part 234
Selling Price/unit
$
$
Direct costs/unit
$
$
Overhead/unit
$
$
Gross margin/unit
$
$
Total
Part 127
Part 234
Total Profit
$
$
Part 5: Another reasonable recommendation to improve profitability. Explain recommendation here:
Per Unit
Part 127
Part 234
Selling Price/unit
$
$
Direct costs/unit
$
$
Overhead/unit
$
$
Gross margin/unit
$
$
Total
Part 127
Part 234
Total Profit
$
$
Part 6: Another reasonable recommendation to improve profitability. Explain recommendation here:
Per Unit
Part 127
Part 234
Selling Price/unit
$
$
Direct costs/unit
$
$
Overhead/unit
$
$
Gross margin/unit
$
$
Total
Part 127
Part 234
Total Profit
$
$
ABC Project-Write-up
You are to assume you are a consultant working for the company. You will want your report to be professional and "ADD VALUE" to the company. Use an executive summary, followed by the detailed report.
Be sure to include the following:
(1)Argue for the use of Activity-based Costing by in this case by:
a)Describing when Activity-based Costing is appropriate and when Traditional Costing is appropriate and when each is not appropriate to use.
b)Discussing what are the strengths and weaknesses of ABC? When is it appropriate to use? What kinds of business situations suggest the need for ABC?
(2)Describe the Activity-based costing system you are recommending. Include a justification for the cost driver selected.
(3)Present your new cost findings. Include both per unit and total cost data. There should be tables with cost information included.
(4)Make strategy recommendations for each product and for the plant. Use the cost and profit numbers to justify these recommendations.
(5)Comment on the validity of the plant manager's concern that competitors are selling below the cost of making Part 127.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started