Question

1 Approved Answer

Activity - Based Costing Total cost per two - day course = R M 5 + R M 4 8 2 + ( R M

Activity-Based Costing
Total cost per two-day course
=RM5+RM482+(RM43.852)+RM380+RM950+RM51.32+RM10
=RM1,966.02 per two-day course
Total cost for two-day course
= RM1,966.0220 courses
= RM39,320.40
2. Total cost per five-day course
=RM5+RM482+(RM43.855)+RM380+RM950+RM51.32+RM10
= RM2,097.57 per five-day course
Total cost for five-day course
= RM2,097.57 x 50 courses
= RM104,878.50
Traditional Costing
Cost per course day = Total cost Total number of days
=RM501,600[(20 courses 2)+(30 courses 5)]
=RM2,640
Total cost for two-day course = Cost per course day x(Number of courses x2)
=RM2,640(20 courses 2)
=RM105,600
Total cost for five-day course = Cost per course day x(Number of courses x5)= RM2,640 courses 5)
=RM396,000
Required: Make a conclusion from the information stated above.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Sustainability

Authors: Gunnar Rimmel

1st Edition

0367478927, 9780367478926

More Books

Students also viewed these Accounting questions