Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Activity Budgeted Cost of Activity Allocation Base Cost Allocation Rate Materials handling. . . $310,000 Number of parts $0.80 Assembling. . . . . .

Activity

Budgeted Cost of Activity

Allocation Base

Cost Allocation Rate

Materials handling. . .

$310,000

Number of parts

$0.80

Assembling. . . . . . . . .

$2,200,000

Direct labor hours

$14.00

Painting. . . . . . . . . . . .

$170,000

Number of painted desks

$5.00

Allen

produced two styles of desks in March: the Standard desk and Unpainted desk. Data for each follow:

Product

Total Units Produced

Total Direct Materials Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard desk. . . . .

5,500

$54,000

121,500

5,700

Unpainted desk. . . .

1,000

$600

31,500

800

pop-up content ends

PrintDone

Allen

Corp. manufactures computer desks in its

Pheonix,

Arizona,

plant. The company uses activity-based costing to allocate all manufacturing conversion costs (direct labor and manufacturing overhead). Its activities and related data follow.

LOADING...

(Click the icon to view the activity areas and related data.)Read the requirements

LOADING...

.

Question content area bottom

Part 1

Requirement 1. Compute the per-unit manufacturing product cost of Standard desks and Unpainted desks. (Complete all input fields. Enter a "0" for any zero amounts. Round your answers to the nearest whole dollar.)

Standard Desk

Unpainted Desk

Direct materials

Materials handling

Assembling

Painting

Total manufacturing cost

Number of units

Manufacturing cost per unit

Part 2

Requirement 2. Premanufacturing activities, such as product design, were assigned to the Standard desks at

$4

each and to the Unpainted desks at

$2

each. Similar analyses were conducted of post-manufacturing activities such as distribution, marketing, and customer service. The post-manufacturing costs were

$22

per Standard and

$20

per Unpainted desk. Compute the full product costs per desk.

Standard Desk

Unpainted Desk

Full product cost per unit

Part 3

Requirement 3. Which product costs are reported in the external financial statements? Which costs are used for management decision making? Explain the difference.

Full product costs

Manufacturing product costs

are reported in the financial statements. Managers use

full product costs

manufacturing product costs

for decisions such as pricing and product emphasis. Full product costs include the

costs of premanufacturing and post-manufacturing activities

direct manufacturing costs only

indirect direct manufacturing costs only

manufacturing costs only

that are expensed as incurred for external reporting. However, these costs often are

assigned to products for internal decisions

ignored for the purposes of internal decision making

.

Part 4

Requirement 4. What price should

Allen's

managers set for Standard desks to earn a

$41

profit per desk?

Sales price per unit - standard desk

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

ABC Finance Coloring Book Familys First Financial Literacy Book

Authors: Jason Conger

1st Edition

1955961026, 978-1955961028

More Books

Students also viewed these Finance questions

Question

What items are necessary to answer a time value of money problem

Answered: 1 week ago

Question

Explain the chemical properties of acids with examples.

Answered: 1 week ago

Question

Write the properties of Group theory.

Answered: 1 week ago