Question

1 Approved Answer

Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3 Side 1 S-----------F Complete Spent $2,000 Side 2 S-----------PF ----F Complete

Activity Day 1 Day 2 Day 3 Day 4 Status End of Day 3
Side 1 S-----------F Complete Spent $2,000
Side 2 S-----------PF ----F Complete Spent $2,200
Side 3 PS--S------PF 40% done, spent $1,000
Side 4 PS---------PF Not yet started
Key S= Actual Start, F=Actual Finish, PS=Planned Start and PF=Planned Finish

You have a project to build a new fence. The fence is four sided as shown. Each side is to take one day to build and is budgeted for $2000 per side. The sides are planned to be completed one after the other. Today is the end of day 3. Using CPI, What is the Estimate at Completion (EAC)?

a.

3495.65

b.

8695.65

c.

8000.00

d.

6000.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Of Electronic Media

Authors: Alan B. Albarran

1st Edition

0495569429, 9780495569428

More Books

Students also viewed these General Management questions

Question

How can sensitivity to pain be altered?

Answered: 1 week ago

Question

=+1. Do you have insurance?

Answered: 1 week ago

Question

=+ 2. Do you have a license and do you have insurance?

Answered: 1 week ago