Question
1 Approved Answer
Activity Description Immediate Predccessor Duration Iweek 12 Cost estimate (R1000) 17 A HAI B B A M16 C B 10 32 D 14 47 E
Activity Description Immediate Predccessor Duration Iweek 12 Cost estimate (R1000) 17 A HAI B B A M16 C B 10 32 D 14 47 E Detail site investigation and survey Detail planning Detail design Preparation of site Relocate services Re-align overhead track electrification Access road and ramp construction Piling Construct foundations and abutments 3 28 F , 4 630 G G D 1 63 H 22 820 H 3 975 K F G 2 720 L c 2 13 M Construct temporary supports to support bridge deck during construction Fabrication planning of structural steel components Manufacture structural steel components (off-site) Transport structural steel components and erect on-site Erect pylons and fill with concrete L 2 1320 N M M 1 433 P 12 840 3 H. K.NP 1,800 R S R 1 1 5 S. 147 S V Construci main span deck en pre-cast concrete beans Cable-stay installation and hit the bridge deck oli temporary supports Removal of temporary supports Electrical system installation Roadway surfacing (paving) Finishing and ancillaries Commissioning - cul-over Fonmal hand-over and ceremony Prese Sign=oft Administrative close Project and (milestone, 142 TU F 4 V 1 w 9 2 W 10021 QUESTIONS 1. Da uz project BeWES AND the duration, the calls start and finish later stant and later finish for each acavity and the critical push and is bulude Marko 2 Compile i sliewing the reduced periode for impairment of the rail Dead and the associated additional costs (Marks Compile a short about the role that he studimana enem team is play to deal with the risk or not Activity Description Immediate Predccessor Duration Iweek 12 Cost estimate (R1000) 17 A HAI B B A M16 C B 10 32 D 14 47 E Detail site investigation and survey Detail planning Detail design Preparation of site Relocate services Re-align overhead track electrification Access road and ramp construction Piling Construct foundations and abutments 3 28 F , 4 630 G G D 1 63 H 22 820 H 3 975 K F G 2 720 L c 2 13 M Construct temporary supports to support bridge deck during construction Fabrication planning of structural steel components Manufacture structural steel components (off-site) Transport structural steel components and erect on-site Erect pylons and fill with concrete L 2 1320 N M M 1 433 P 12 840 3 H. K.NP 1,800 R S R 1 1 5 S. 147 S V Construci main span deck en pre-cast concrete beans Cable-stay installation and hit the bridge deck oli temporary supports Removal of temporary supports Electrical system installation Roadway surfacing (paving) Finishing and ancillaries Commissioning - cul-over Fonmal hand-over and ceremony Prese Sign=oft Administrative close Project and (milestone, 142 TU F 4 V 1 w 9 2 W 10021 QUESTIONS 1. Da uz project BeWES AND the duration, the calls start and finish later stant and later finish for each acavity and the critical push and is bulude Marko 2 Compile i sliewing the reduced periode for impairment of the rail Dead and the associated additional costs (Marks Compile a short about the role that he studimana enem team is play to deal with the risk or not
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started