Activity Duration (Days) Direct cost (P) Activity Name Normal Crush Normal Crush 1-2 Trench 12 10 3,600 3,880 1-4 Footing 18 14 4,600 5,000 1-3
Activity Duration (Days) Direct cost (P)
Activity Name Normal Crush Normal Crush
1-2 Trench 12 10 3,600 3,880
1-4 Footing 18 14 4,600 5,000
1-3 Foundation 9 6 2,600 3,200
2-4 3 course 7 6 1,800 1,950
2-5 Window level 12 10 3,000 3,240
4-5 Roof level 13 9 36,000 4,240
3-5 Roofing 7 5 1,900 2,400
21,100 23,910
a) Calculate the normal cost to complete the project if the fixed cost amounts to
P200/day.
b) Calculate the minimum cost of the project if it is to be completed in 22 days.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started