Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Activity Duration (Days) Direct cost (P) Activity Name Normal Crush Normal Crush 1-2 Trench 12 10 3,600 3,880 1-4 Footing 18 14 4,600 5,000 1-3

Activity Duration (Days) Direct cost (P)

Activity Name Normal Crush Normal Crush

1-2 Trench 12 10 3,600 3,880

1-4 Footing 18 14 4,600 5,000

1-3 Foundation 9 6 2,600 3,200

2-4 3 course 7 6 1,800 1,950

2-5 Window level 12 10 3,000 3,240

4-5 Roof level 13 9 36,000 4,240

3-5 Roofing 7 5 1,900 2,400

21,100 23,910

a) Calculate the normal cost to complete the project if the fixed cost amounts to

P200/day.

b) Calculate the minimum cost of the project if it is to be completed in 22 days.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Using Microsoft Excel and Access 2016 for Accounting

Authors: Glenn Owen

5th edition

1337109048, 1337109045, 1337342149, 9781337342148 , 978-1337109048

More Books

Students also viewed these Accounting questions

Question

6. What information processes operate in communication situations?

Answered: 1 week ago

Question

3. How can we use information and communication to generate trust?

Answered: 1 week ago