Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F

Activity Duration Predecessor Cost
A 8 - 25000
B 12 - 42000
C 7 A 18000
D 10 A 27000
E 14 B,C 46000
F 5 B,C 12000
G 3 D,E 7000
H 12 D,E 42000
I 10 F,G 36000

Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made.

a) Find the net present value of the project at a discount rate of 3% per period.

Activity Crashed Duration Normal Duration Crashed Cost Normal Cost
C 5 7 22000 18000
E 11 14 58000 46000
I 8 10 44000 36000

b)Given an option is available to reduce the duration of following activities at additional cost, what would be the optimal project duration? Assume indirect costs to be negligible.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing CPA Exam Review

Authors: Becker

1st Edition

1943628696, 978-1943628698

More Books

Students also viewed these Accounting questions

Question

Explain how an embedded audit module works.

Answered: 1 week ago