Activity Duration Predecessor Cost A 8 - 25000 B 12 - 42000 C 7 A 18000 D 10 A 27000 E 14 B,C 46000 F
Activity | Duration | Predecessor | Cost |
A | 8 | - | 25000 |
B | 12 | - | 42000 |
C | 7 | A | 18000 |
D | 10 | A | 27000 |
E | 14 | B,C | 46000 |
F | 5 | B,C | 12000 |
G | 3 | D,E | 7000 |
H | 12 | D,E | 42000 |
I | 10 | F,G | 36000 |
Consider the following project data. Assume costs are incurred upon completion of an activity. At the end of the project a lump sum payment of 340,000 is to be made.
a) Find the net present value of the project at a discount rate of 3% per period.
Activity | Crashed Duration | Normal Duration | Crashed Cost | Normal Cost |
C | 5 | 7 | 22000 | 18000 |
E | 11 | 14 | 58000 | 46000 |
I | 8 | 10 | 44000 | 36000 |
b)Given an option is available to reduce the duration of following activities at additional cost, what would be the optimal project duration? Assume indirect costs to be negligible.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started