Question
1 Approved Answer
Activity Minutes Processing order 25 Waiting for copying to begin 29 Copying 21 Waiting for binding 31 Binding 9 Packing for customer 4 (a) Calculate
Activity | Minutes |
Processing order | 25 |
Waiting for copying to begin | 29 |
Copying | 21 |
Waiting for binding | 31 |
Binding | 9 |
Packing for customer | 4 |
(a) | Calculate the delivery cycle time. | |
|
(b) | Calculate the manufacturing cycle time. | |
|