Activity Normal Time Manpower requirement 0-1 2 4 1-2 3 3 1-3 4 3 2-4 2 5
Fantastic news! We've Found the answer you've been seeking!
Question:
Activity | Normal Time | Manpower requirement |
0-1 | 2 | 4 |
1-2 | 3 | 3 |
1-3 | 4 | 3 |
2-4 | 2 | 5 |
3-5 | 4 | 3 |
3-6 | 3 | 4 |
4-7 | 6 | 3 |
5-7 | 6 | 6 |
6-8 | 5 | 2 |
7-9 | 4 | 2 |
8-9 | 4 | 9 |
Using the above table information ,
- Re-arrange the activities suitably in order to reduce the existing total manpower.
- If only 9 workers are available for the execution of the project, then re-arrange the activities suitably for leveling the manpower resource.