Question

1 Approved Answer

Activity Normal Time ( weeks ) Crash Time ( weeks ) Normal Cost Total Cost with Crashing Immediate Predecessor ( s ) A 4 3

Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessor(s)
A 43 $2,100 $2,750-
B 21 $2,300 $2,900-
C 33 $500 $500-
D 84 $2,400 $2,700 A
E 63 $800 $1,100 B
F 32 $3,200 $4,700 C
G 42 $1,500 $2,000 D, Eb) The total cost required for completing this project on normal time=$
enter your response here

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books