Activity Optimistic Most Probable Pessimistic A 4 5 6 B 2.5 3 3.5 C 7 8 9 D 5 5.5 9 E 5 7 9

Activity Optimistic Most Probable Pessimistic
A 4 5 6
B 2.5 3 3.5
C 7 8 9
D 5 5.5 9
E 5 7 9
F 2 3 4
G 7 9 11
H 7 8 15

To help with preparations, a couple has devised a project network to describe the activities that must be completed by their wedding date. The following table lists the activity time estimates (in weeks) for each activity. (See chart attached) Based only on the critical path, what is the estimated probability that the project will be completed within the given time frame? (Round your answers to four decimal places.) (a)Within 21 weeks? B)Within 23 weeks? (c)Within 27 weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting For Beginners Learn Easy And Fast Accounting Principles

Authors: Dan Wilson

1st Edition

1700199900, 978-1700199904

More Books

Students also viewed these Accounting questions

Question

Find the median for the set of measurements 2, 9, 11, 5, 6, 27.

Answered: 1 week ago