ACTIVITY PREC. ACT. TIME ESTIMATES (days) ABCDEFG A A A C B to 1 tml 2 3 tp 11 3 1 1 4 4
ACTIVITY PREC. ACT. TIME ESTIMATES (days) ABCDEFG A A A C B to 1 tml 2 3 tp 11 3 1 1 4 4 1 0 _ 2 1 2 1 1 2 2 Show all work: 1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.] 2) By using Te and ES, EF, LF, LS, state TIMES on the network. Find the slack of each activity and clearly identify the Critical Path. 3) Find the average completion time ( Xbar) and (s Sigma), the standard deviation, for the project- round off the standard deviation to the nearest hundredth: two decimal places. 4) What is the completion time at 95% Confidence Interval? 5) What is the likelihood of this project being completed in more than 8 days? 6) What is the likelihood of this project being completed BETWEEN 9 and 11 days? ANSWERS: RECAP COMPLETED NETWORK with: Drawing, Te, Times, and CP clearly shown on network. CP: xbar: Sigma: CI: 95% [ ____ to _____] ND: Pd>7: P8>d >7
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started