Question
ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A ----- 2 4 6 B ----- 2 5 8 CB123 DA222 E C,D 4
ACTIVITY PREC. ACT. TIME ESTIMATES (days)
to tml tp te A ----- 2 4 6 B ----- 2 5 8 CB123 DA222 E C,D 4 5 6 FE333 GF123 HE147
I G,H 2 5 14
1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]
2) CLEARL Y show all TIMES in the network. By using ES, EF , LF , LS, find the slack of each activity and IDENTIFY the CRITICAL PATH.
3) Find the completion time ( - Xbar) and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.
4) Find 68% and 99.7% Confidence Intervals.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started