ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A ----- 2 4 6 B ----- 2 5 8 CB123 DA222 E C,D 4

ACTIVITY PREC. ACT. TIME ESTIMATES (days)

to tml tp te A ----- 2 4 6 B ----- 2 5 8 CB123 DA222 E C,D 4 5 6 FE333 GF123 HE147

I G,H 2 5 14

1) Construct a PERT network. [NOTE: This is the most crucial part of the exercise. Make sure you have the correct network before proceeding to the next sections.]

2) CLEARL Y show all TIMES in the network. By using ES, EF , LF , LS, find the slack of each activity and IDENTIFY the CRITICAL PATH.

3) Find the completion time ( - Xbar) and the standard deviation () for the project round off the standard deviation to the nearest hundredth: two decimal places.

4) Find 68% and 99.7% Confidence Intervals.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Elementary Symbolic Logic

Authors: William Gustason, Dolph E Ulrich

2nd Edition

1478616857, 9781478616856

More Books

Students also viewed these Mathematics questions

Question

6. How can hidden knowledge guide our actions?

Answered: 1 week ago

Question

7. How can the models we use have a detrimental effect on others?

Answered: 1 week ago