Activity Preceding Activity Duration Start 0 A Start 3 B A 3 C A 4 D A 5 E B,C 3 F B,C,D 6 G
Activity Preceding Activity Duration Start 0 A Start 3 B A 3 C A 4 D A 5 E B,C 3 F B,C,D 6 G E,F 5 H G 4 Finish H 0 What is critical path what is the slack on activity C what is late start for activity f what hapeens if B is increased to 7 days