Activity Predecessors a m b A 2 5 8 B 6 7 8 C A 1 2 3 D A , B 6 7 8

Activity
Predecessors
a
m
b
A
2
5
8
B
6
7
8
C
A
1
2
3
D
A,B
6
7
8
E
C
2
5
8
F
C
1
2
9
G
D,E
4
5
12
H
F,G
2
3
4
From the table above find the flowing answers.
1. Construct the project Network
2. Find the expected duration and Variance of each activity
3. Find the critical path and expected project completion time
4. What is the probability of completion the project on or before 22 weeks?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Service Management Operations, Strategy, Information Technology

Authors: James A Fitzsimmons, Mona J Fitzsimmons

6th Edition

0077228499, 9780077228491

More Books

Students also viewed these General Management questions

Question

What is a per-packet key system?

Answered: 1 week ago