Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Activity Predessor Duration A 7 B 6 C 33 D B 24 E C 4.1 F D 9 G A,B 12 H E 10 I
Activity Predessor Duration A 7
B 6 C 33 D B 24 E C 4.1 F D 9 G A,B 12 H E 10 I G 7 J F,G 10
Activity | Predessor | Duration | |
A |
| ||
B | 6 | ||
C | 33 | ||
D | B | 24 | |
E | C | 4.1 | |
F | D | 9 | |
G | A,B | 12 | |
H | E | 10 | |
I | G | 7 | |
J | F,G | 10 |
Use the information above and draw a network diagram showing the L/S, E/S, E/F, L/F, Slack, and Critical Path